Thursday, May 3, 2012

Paramount Blvd. Brige Repair Project


  • All of the 34 concrete girders have been placed. 
  • False work has been stripped away from the five columns. 
  • Crews are now in placing steel rebar on top of the girders in preparation of the construction of the bridge deck.
  • A new drainage system will be installed in the median under the bridge.
Here's a video of the construction crews placing the precast girders.