Wednesday, May 9, 2012

Paramount Boulevard Bridge Update - May 9, 2012

Work is moving at a steady pace, it is possible that the bridge could open before June 2012, but with all construction projects, there could be delays.  Our project staff and Ortiz Enterprises Inc., the contractor, have said that the project is still on schedule.

So far construction crews have poured the deck for the bridge.  It will take several days to cure.  Next crews will build the approach slabs to connect the existing roadway to the new bridge.