At 3:40 a.m. today the North Broadway and Grand Avenue on-ramps were reopened to daytime traffic.  The ramps will still close intermittently at night through mid-April.  These ramps were part of multiple locations along US 101 closed as part of a project to replace the existing bridge rails, bringing them into compliance with current safety standards.

The bridge rail project is 75% complete.  The entire project completion is estimated late spring 2015. Construction activities for the next two weeks are as follows.  This work schedule is subject to change:

March 16 through March 30
Monday through Friday from 9 a.m. to 3 p.m.

Southbound US 101
Highland Avenue/Cahuenga Boulevard off-ramp – Estimated completion mid-May
Vine Street/Franklin off-ramp – Estimated completion mid-April.

March 16 through March 30
Intermittent night closures, Monday through Friday from 9 p.m. to 5 a.m. 

Northbound US 101

North Broadway on-ramp – Open daily

State Route 110/US 101
Grand Avenue on-ramp SR-110 – Open daily  

Closures include lanes and ramps within the project parameters.  Some weekend work may be required, excluding holidays.  Motorists, local businesses and residents may experience noise and vibration from construction activities.  Expect traffic delays, plan ahead and leave early.  The contractor for this $4.3 million project is Peterson-Chase of Irvine, California. 